JERSEYVILLE - Jersey Community Middle School will reopen to students and staff Wednesday, Nov. 18, 2026, after a ruptured water pipe flooded about one-third of the building, Jersey CUSD No. 100 Superintendent Brad Tuttle announced in a Monday, Nov. 16, 2026, letter to families.
Classes at the middle school will remain canceled Tuesday, Nov. 17, 2026, while teachers unpack, organize classrooms and make final preparations for students’ return. Tuttle said the building has been cleared for occupancy following water removal, drying, sanitization and inspections.
Don't miss our top stories and need-to-know news everyday in your inbox.
"The main water pipe ruptured beneath the concrete slab in the school’s southwest corner about 11:45 p.m. Wednesday, Nov. 11," Tuttle said. "When the problem was discovered at 6 a.m. Thursday, Nov. 12, facilities staff shut off the water and brought in SERVPRO’s Disaster Recovery Team for emergency mitigation.
"The break left roughly 1 to 2 inches of standing water across about 35,000 square feet, including the main office, media center, and several classrooms.
"Crews removed standing water, installed a new exterior water main pipe and worked room by room to dry and sanitize affected areas. The district said the work followed ANSI/IICRC S500 water-damage restoration standards.
"Affected surfaces were vacuumed with HEPA-filtered equipment and treated with an EPA-registered disinfectant intended for use in schools. HEPA-filtered air scrubbers operated in work zones, and technicians used infrared cameras and moisture meters to identify and check moisture behind walls and beneath floors."
Tuttle continued and said the Regional Office of Education toured the school and authorized students’ return.
"District architects also inspected the building and are processing emergency Health/Life Safety amendments to support continuing restoration," he said. "An industrial hygienist conducted environmental testing to verify that mitigation work met safety standards, the district said.
"Some restoration work remains, and affected areas will look different when students return. Crews removed damaged carpeting, rugs, vinyl flooring, cove base and porous furniture. Exposed concrete floors are covered with heavy-duty Ram Board. In areas where the bottom 2 feet of drywall were removed, new drywall and insulation have been installed.
"New flooring, drywall finishing, painting and furniture replacement are planned for upcoming school breaks and weekends to avoid disrupting instruction," according to the district.
Tuttle added that the district is seeking state approval for emergency days to cover instructional days missed because of the flooding.
"Families will receive updates on the districtwide calendar once that process is finalized," he said.
Principal Niki Egelhoff will send middle school families a separate message through Parent Square with details about Wednesday’s arrival procedures, classrooms and extracurricular activities.